Construction progressing well

Completed Foundation

Construction work is in full swing at both the wind farm site and on the grid connection route. 11 wind turbine foundations have been constructed and works are well underway on the remaining five.

The wind farm access tracks are now complete ready for the delivery of the wind turbine components expected to begin later this month.

Work is also progressing well on the grid connection route with over 85% of the cable duct work complete.